Round Rock Texas Banner
File #: 13-593   
Type: Resolution Status: Passed
File created: 7/24/2013 In control: City Council
On agenda: 8/22/2013 Final action: 8/22/2013
Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Cash Construction for the Chisholm Trail Road Phase 3 Improvements Project.
Indexes: RR Transportation and Economic Development Corporation (Type B)
Attachments: 1. Resolution, 2. Exhibit A
Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Cash Construction for the Chisholm Trail Road Phase 3 Improvements Project.
 
Body
On February 14, 2013, the City Council awarded the construction services contract for Chisholm Trail Road Phase 3 to Cash Construction at a cost of $3,354,101.  The initial contract was for the construction of a five lane urban roadway with curb and gutters and a three lane driveway for the Sports Complex.
 
Quantity Adjustment/Change Order No. 1 deducts 192 linear feet of twenty-four inch (24") drill shaft at a cost reduction of $38,400.  Added to the construction contract were 192 linear feet of thirty inch (30") drill shaft; one storm trooper frame and installation of a control manhole; one storm trooper re-pour and installation of a control manhole; and additional fencing for the Lang property at a cost of $94,190.  The cost of Quantity Adjustment/Change Order No. 1 would be $55,790.
 
The total cost of the construction contract would be $3,409,891.
 
Cost: $55,790.00
Source of Funds: Round Rock Transportation and Economic Development Corporation
 
Recommended Action
Staff recommends approval.