Round Rock Texas Banner
File #: 13-628   
Type: Resolution Status: Passed
File created: 8/5/2013 In control: City Council
On agenda: 8/22/2013 Final action: 8/22/2013
Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with APAC-Texas, Inc. for the 2012 Neighborhood Revitalization Project.
Indexes: CDBG HUD Entitlement Grants, General Self-Financed Construction
Attachments: 1. Resolution, 2. Exhibit A, 3. Map
Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with APAC-Texas, Inc. for the 2012 Neighborhood Revitalization Project.
 
Body
In 2012 the City of Round Rock approved the Street Maintenance Program (Neighborhood Revitalization) that is a street rehabilitation project that provides an essential function in maintaining our roadways.  The project that was currently completed provided pavement and concrete repairs in the Green Hill Subdivision.  This project also qualified for CDBG funds that were used for this roadway rehabilitation, and supplemented our General fund.
The City of Round Rock approved a contract with APAC-Texas, Inc. for this project in the amount of $895,090.00. During the course of the project, City Staff, and APAC-Texas, Inc. were able to define areas that had been identified for repairs, that were not as critical as previously thought. The result was a reduction in cost of $94,984.88.
Cost: $94,984.88
Source of Funds: CDBG and General Self-financed Construction
 
Recommended Action
Staff Recommends Approval.