Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 2 with Cash Construction Company, Inc. for the Chisholm Trail South Improvements (Old Town) Project.
Body
The Chisholm Trail South Improvements Project included upgrades to Chisholm Trail Road between Sam Bass Road and RM 620. The scope of work included pavement reconstruction, sidewalk improvements, and upgrades to utility and drainage infrastructure. Construction began in July 2025 and the roadway was opened to the driving public in November 2026.
Quantity Adjustment/Change Order (QA/CO)No. 2 provides for payment of additional work necessary to address unforeseen field conditions and improve project connectivity and ADA compliance. The additional work includes:
- Removal and replacement of a deteriorated 10' x 30' section of concrete pavement and a concrete sidewalk located between the limits of this project and the previously completed adjacent parks project.
- Additions of ADA ramps at the Sunset Boulevard and Chisholm Trail South intersection to improve ADA compliance for pedestrian crossings.
- Additional concrete sidewalk at two businesses to extend the stamped concrete sidewalk approximately 1 to 2 feet to the edge of the right-of-way. This work provides a consistent transition and eliminates small remaining sections of the existing red brick sidewalk.
An additional 20 calendar days was also added to the contract to allow the contractor sufficient time to complete this additional work. The original contract price was $4,261,098. QA/CO No. 2 increases the contract amount by $126,940.28 bringing the total contract value to $4,694,509.60.
Cost: $126,940.28
Source of Funds: RR Transportation and Economic Development Corporation