This amendment to the Transportation Capital Improvement Program includes the following:
New Projects:
1) Arterial H Utility Reimbursement, $300,000 for right-of-way.
2) Downtown Improvements Project, $120,000 for infrastructure planning.
3) Gander Mountain Way, $100,000 for plan development.
Project Decreases:
1) Creek Bend Boulevard, budget reduction of $3,500,000, using funds on projects about to be bid for construction ($1,300,000 transfered to Chisholm Trail Phase 3).
2) CR 113/Kiphen Road/Old Settlers Boulevard, budget reduction of $268,759, project closed out.
3) FM 1460/A.W. Grimes Boulevard, budget reduction of $256,782, project closed out.
4) Arterial A/Kenney Fort Boulevard, budget reduction of $1,000,000, project nearing completion.
5) FM 3406, budget reduction of $1,500,000, project funded out of remaining General Obligation Bonds.
6) Southwest Downtown Projects 2,3 and 7, reduce budget $17,251, project closed out.
7) IH 35 Ramp Reversals, reduce budget by $7,200,000, seeking funding from state or Federal Highway Administration for this project.
8) 2012-2016 Street Maintenance, reduce budget by $4,302,825, to focus on more local street improvements.
9) S. Mays at Gattis, reduce budget by $175,210, to cover actual contracted engineering costs (funds were transfered to bottlenecks).
Project Increases:
1) Bottlenecks, budget increase of $675,210, to fund construction of bottleneck projects throughout the community.
2) Cypress Boulevard, increase budget by $1,400,000, higher than expected estimated construction costs.
3) University Boulevard, increase budget by $750,000, to complete design work for the project.
4) Mays Street Reconstruction, increase budget by $4,000,000, to cover increased construction costs.
5) Southwest Downtown Phase 4, increase budget by $3,000,000, to cover increased construction costs.
6) Consulting, increase budget by $150,000, to cover future planning activities.
7) Quiet Zones, increase budget by $2,000,000, to pay for construction of the project.
8) Arterial Sidewalks, increase budget by $150,000, to add sidewalks along South Mays Street.
9) Chisholm Trail Phase 3, increase budget by $1,300,000 from for additional construction costs.
These amendments to the TCIP result in a net reduction to the overall TCIP budget of -$4,275,617.
Recommended Action
Staff recommends approval.