Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Texas Pride Utilities, LLC for the Cycle 3 - Basins 4 & 5 Wastewater Main Rehabilitation Project.
Body
The City of Round Rock must evaluate the wastewater system inside the Edwards Aquifer recharge zone every five years to comply with the Texas Commission on Environmental Quality requirements. The elimination of defects inside the Edwards Aquifer recharge zone protects the Edwards Aquifer and reduces inflow and infiltration entering the City's wastewater collection system, thereby reducing the City's treatment cost. The City has divided the Edwards Aquifer recharge zone into five wastewater basins. Each wastewater basin contains numerous sub-basins. This project inspected and evaluated Basins 4 and 5 for defects.
In February 2024, the City of Round Rock awarded the wastewater rehabilitation contract to Texas Pride Utilities, LLC. During construction, several sections of the project were able to be removed or reduced based on field investigations including reduce length of pipeline replacement at several locations, removal of a manhole drop, or modification to the repair procedure. Additionally, this quantity adjustment corrects a quantity error in the bid documents for 6-inch to 8-inch pipe bursting that was identified during construction.
The difference between the original and adjusted contract price is -$526,509.45. This quantity Adjustment/Change Order No. 1 includes quantity adjustments of -$558,976 plus change orders of $32,466.55 which reduces the original contract amount from $1,965,380 to $1,438,870.55.
Cost: - $526,509.45
Source of Funds: Self-Financed Wastewater Construction