Round Rock Texas Banner
File #: 2024-210   
Type: Resolution Status: Agenda Ready
File created: 8/5/2024 In control: City Council
On agenda: 8/22/2024 Final action:
Title: Consider a resolution approving the action of the Round Rock Transportation and Economic Development Corporation (Type B) in approving a portion of the Old Settlers Park Improvements Project as a Type B project pursuant to the Local Government Code.
Indexes: 2023 General Obligation Bonds, General Self-Financed Construction, RR Transportation and Economic Development Corporation (Type B)
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider a resolution approving the action of the Round Rock Transportation and Economic Development Corporation (Type B) in approving a portion of the Old Settlers Park Improvements Project as a Type B project pursuant to the Local Government Code.

Body
The Old Settlers Park project includes several major additions to the park, including improvements that qualify as projects for the RRTEDC.

The total project costs are expected not to exceed $188 million, and include:

RRTEDC (Type B) Funded - $15 million
· $4.5 million to move and reconstruct the multipurpose Apex Fields used for soccer, cricket, football, etc.
· $10.5 million of the estimated $21.7 million to construct track and field facilities adjacent to the new recreation center complex.

Voter Approved GO bonds - $150 million
· Constructing, improving, extending, expanding, upgrading and/or developing City parks, recreation and sports projects and facilities, comprised of:
o Lakeview Area Improvements & Pavilion
o New Recreation Center Complex
o Track and Field Facilities
o Rock’N River Expansion
o Tennis and Pickleball Courts
o Maintenance Yard Relocation and Expansion
o Multipurpose Complex Expansion

General Self-Finance Construction Fund - $23 million
· Additional added value for the new recreation center complex, Rock’N River expansion, tennis and pickleball courts, and maintenance yard expansion.

The Type B board approved $34.5 million for the Harrell Parkway road project in February 2024, which is also an integral part of the entire OSP Project.

This agenda item is to approve the adoption of this plan by the Type B Board at the August 22, 2024, meeting.

The Old Settlers Park project is expected to break ground and be completed in phases as follows:
· Harrell Parkway construction estimated to begin October 2024 and complete in November 2025.
· Apex Fields movement and reconstruction estimated to begin October 2024 and complete in July 2025. (Part of Ha...