Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Braun and Butler Construction Inc. for the Griffith Remodel and Paseo Project.
Indexes: General Self-Financed Construction
Attachments: 1. Resolution, 2. Exhibit A, 3. 1295

Title

Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Braun and Butler Construction Inc. for the Griffith Remodel and Paseo Project.

 

Body

During the remodel of the Griffith Building, the windows along the South and East were discovered to be leaking causing mold in the walls of the structure. Change Order No. 1 with Braun and Butler Construction Inc. is to replace 19 windows,  install new flashing, and waterproofing. The new windows will have the same shape, arching at the top, to maintain the historic appearance as the old windows. All mold has been remediated by a professional contractor.

 

Cost: $303,932.00