Skip to main content
Round Rock Texas Banner
File #: 2025-162   
Type: Resolution Status: Agenda Ready
File created: 6/9/2025 In control: City Council
On agenda: 6/26/2025 Final action:
Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Capital Excavation Company for the Wyoming Springs Segment 1 Project.
Indexes: RR Transportation and Economic Development Corporation (Type B)
Attachments: 1. Resolution, 2. Exhibit A, 3. Map, 4. 1295
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Capital Excavation Company for the Wyoming Springs Segment 1 Project.

Body
The new Wyoming Springs Segment 1 roadway project will connect the existing Wyoming Springs Boulevard at its intersection with Creek Bend Boulevard/Brightwater Boulevard to the intersection with FM 3406/Old Settlers Boulevard.

Quantity Adjustment/Change Order (QA/CO) NO. 1 includes the following items:

- The construction of a concrete cap to encapsulate/protect the existing Atmos Energy natural gas pipeline running across the project. A specially designed encroachment facility is required to protect the pipeline. This design has been approved by Atmos Energy, post letting and is now being included as a change order cost to the project. In negotiations with Atmos, the design was revised to allow a considerable savings. Initial engineer estimate was $475,000, but the actual negotiated cost is $171,021.56.

- Contractor proposed switching from C110 to C153 waterline fittings which created a savings of $44,356.12. This savings were evenly divided between the City and the Contractor (-$22,178.06/each).
After the contract was signed, the contractor and structural consultants began working with the City to improve upon the constructability of the bridge fascia panels on the Brushy Creek bridges. The new design proposes the use of the new modified TX54 girders to construct a stronger and more stable fascia panel connection. These design changes will also improve the safety and longevity of the structure. Cost for this item is $96,642.00.

- The work on a 30-inch waterline relocation needed to be accelerated to meet the revised schedule from the adjoining Williamson County road project on Sam Bass Drive. The City's contractor accelerated their schedule/work by adding an extra crew and working extra hours to ensure the line was ready when the repair work on the Williamson County project...

Click here for full text