Consider a resolution rejecting all bids submitted for the Red Bud Lane Right Turn Lane Project.
Body
In the continuing effort to improve traffic flow on our roadways, the Transportation Department developed plans for a right turn lane at Gattis School Road and Red Bud Lane. This project included the addition of a northbound right turn lane and pavement repairs in the intersection.
The City held the bid opening on December 1, 2015, where two sealed bids were received. The engineer’s cost estimate for this project was $438,562.00; the bids were from Patin Construction at $894,000.00, and Central Road and Utility for $1,185,656.00.
After careful review and certification of the attached bid tabulation and discussion with the consulting engineer on this project, the Transportation Department staff recommends that all bids be rejected at this time.
Recommended Action
Staff recommends approval.