Consider a resolution authorizing the Mayor to execute a First Amendment to the Standard Form of Agreement between Owner and Construction Manager for the Old Settlers Park Buildout Project.
Body
The original Construction Manager at Risk Agreement with SpawGlass Contractors Inc. Included a pre-work allowance for purchasing long lead items. During design, it was identified that ordering, fabrication, and delivery time for the Contech Underpass and Pioneer Bridge would exceed the construction schedule. SpawGlass was able to use the prework allowance to start fabrication of the underpass and bridge to meet the construction schedule and minimize delays to the Harrell Parkway project. This First Amendment to the Standard Form Agreement is to replenish the pre-work allowance for other long lead item purchases that have not been identified.
Cost: $564,166.00