Consider a resolution authorizing Mayor to enter into a Standard Form of Agreement between Owner and Contractor with John King Construction for the Rabb House Redevelopment Project.
 
Body
The City received seven competitive sealed prposals from General Contractors on the Re-Bid of the Rabb House Redevelopment Project.  The review committee consisted of Rick Atkins, David Buzzell, Chad McDowell, Larry Madsen, Keith Kickman and Ryan Hansanuwat of KAH Architechts met and named John King Costruction as the number one proposer.  John King Construction was the lowest in price and graded out overall as the number one proposal.  The total proposal amount is $2,395,411.00 and the following is the breakdown:
 
Base Bid                                           $1,818,549.00
Alternate #1 Parking Area #1                              $   172,960.00
Alternate #2 Parking Area #2                              $   118,816.00
Alternate #3 Amphitheater Stage & Associated Walks      $   289,183.00
Alternate #4 Remove Wheelchair Lift & add Associated
walks (deduct)                                           $    -4,097.00
 
Total Proposal                                          $2,395,411.00
 
Cost: $2,395,411.00
Source of Funds: General Self-financed Construction
 
Recommended Action
Staff recommends approval