Title
Consider a resolution authorizing the Mayor to execute a contract with Joe Bland Construction, LLC for the Red Bud Lane North Project.
Body
The bid opening for City of Round Rock, North Red Bud Lane was conducted on Tuesday September 10, 2024. Eight bids were received for North Red Bud Lane and the bid tabulation is attached for information. Joe Bland Construction LLC is the apparent low responsive bidder for this project with a bid of $26,835,030.00. Contractors for this project were subject to the minimum qualifications outlined in the Project Manual and the apparent low responsive bidder meets those qualifications.
Based solely on the bids, as submitted, it is hereby recommended that the bid and construction contract for the project referenced above be awarded to Joe Bland Construction LLC.
Total Bids Received:
Joe Bland Construction: $26,835,030.00
Smith Contracting Co: $31,511,410.52
Patin Construction: $31,850,148.50
DeNucci Constructors: $32,735,478.00
Chasco Constructors: $32,869,966.00
Jordan Foster Construction: $33,625,368.63
Austin Engineering Co: $35,028,599.58
Capital Excavation Co: $35,666,086.45
Cost: $26,835,030.00
Source of Funds: RR Transportation and Economic Development Corporation