Consider a resolution authorizing the Mayor to execute a Contract for Engineering Services with K. Friese & Associates, Inc. for the McNutt Creek C9 Project.
Body
The northeast area of Round Rock, specifically east of A.W. Grimes Boulevard and north of County Road 172, does not currently have water and wastewater utilities in place to serve this area. The City recently completed Water and Wastewater System Master Plans that have identified the necessary improvements for utilities in this part of Round Rock.
The McNutt Creek C9 Project is one of the projects that will extend wastewater infrastructure in the northeast quadrant of Round Rock. This Professional Services Contract is for the Design and Construction Phase Services of approximately 6,300 linear feet of 24-inch wastewater line starting at the northern termination point of McNutt Creek C3 wastewater line and generally running north, terminating at a point just north of University Boulevard Right-of-Way. City staff recommends awarding this Contract to K. Friese & Associates, Inc. for the amount of $233,219.
Cost:$233,219.00
Source of Funds: Self-financed Wastewater Construction
Recommended Action
Staff recommends approval.