Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 2 with Chasco Constructors for the Oakmont Drive Extension Project.
Body
The City issued a NTP to Chasco Contractors on August 2, 2021 for the Oakmont Extension Project.
Change Order #1 was for the addition of a valley gutter at Sunrise and Oakmont Drive to aid in the drainage of the street, adjusting a manhole to grade, and to construct a doghouse protective cover to bridge over the existing waste water line that the roadway is spaning. It also included the removal of curb and gutter and HMAC. The net of the change order and quantity adjustment was $30,933.00 and brought the total contract price to $2,480,927.00.
Change Order #2 is for the relocation adjustment and lowering of the waterline and to relocate and adjust the existing waste water line and install a new manhole. The Quantity Adjustment is in the amount of $35,614.00 and the Change Order portion is $118,588.75. The total is $154,202.75. Utilities portion for the waste water relocation is $24,085.00 and Transportation's portion is $130,117.75.
Cost: $154,202.75
Source of Funds: RR Transportation and Economic Development Corporation & Self-Financed Wastewater Construction