Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Lone Star Sitework, LLC. for the E. Main Street Gaps Sidewalk Project.
Body
The East Main Street Gaps Sidewalk Project provides a sidewalk along Main Street and Circle Drive. The original project planned to replace driveways including culverts as well. The original contract was $ 682,085.75.
Change order 1 provides additional quantity for driveways, curb, rip rap, sidewalk, ramps, and removal of culverts, SETs, manhole adjustments and irrigation repair. The project also added 2 steel bridges to span manholes and drainage, and upgrading the rebar within the sidewalk along the side of the road. This is a closeout change order, work is complete and accepted. The total additional cost for Change Order 1 is -474.43
New contract total: $681,611.32.
Cost: -$474.43
Source of Funds: RR Transportation and Economic Development Corporation