Title
Consider a resolution authorizing the Mayor to execute a Contract with Dan Williams Company for the CR 112 East Project.
Body
The proposed CR 112 (Avery Nelson Parkway) roadway improvements is a high priority Arterial in the Northwest quadrant of the City. The limits of this segment of CR 112 is from CR 117 heading east to CR 110. This roadway is being constructed as an urban 6-lane divided facility with select median openings for sideroads. This segment will be constructed concurrently with the project that starts at AW Grimes and ends at CR 117.
On October 15th the City held a bid opening for the CR 112 East Improvements Project. The City received six bids for the project. The base bid prices ranged from $20,434,128.40 to $22,678,614.30. The low bidder was Dan Williams at $20,434,128.40.
Total Bids Received:
Dan Williams: $20,434,128.40
Jordan Foster: $20,668,424.90
Chasco Constructors: $20,979,799.30
Patin Construction: $21,729,333.45
Capital Excavation: $22,069,999.60
Joe Bland Construction: $22,678,641.30
Cost: $20,434,128.40
Source of Funds: RR Transportation and Economic Development Corporation