Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with John King Construction, Ltd. for the Fire Station No. 1 Project.
Body
During the earthwork construction for Fire Station No. 1, groundwater was encountered. To mitigate groundwater concerns and possible future building settlement, a solution of compacted bull rock was designed by the geotechnical engineer and structural engineer. This change order is for $62,514.00 in material and placement for the Fire Station No. 1 building pad stabilization for ground water. Also, Oncor's easement for primary power to the building conflicted with other utilities easements on the site. This change order is for $15,717.00 to mitigate easement issues by resequencing construction, moving utilities, relocating onsite materials, and relocating the construction trailer. No days are added to the construction schedule. Total change order amount with markup is $86,789.00.
Cost: $86,789.00
Source of Funds: Future General Obligation Bonds