Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 2 with Cash Construction Company, Inc. for the Gattis School Road, Segment 3 Project.
Body
An open bid was held by the City on February 27, 2024 for the Gattis School Road, Segment 3 Project. The low bidder was Cash Construction with a bid of $26,735,973.35. The Notice to Proceed was written in August 26, 2024.
The change order portion of Quantity Adjustment/Change Order (QA/CO) No. 1 was for additional pedestrian poles for the Double Creek Drive intersection, restocking fee for unused 30-inch steel casing, and utility pole relocation due to conflicts. The total amount for the Change Order was $43,932.64.
The quantity adjustment portion of QA/CO No. 1 was for additional 42-inch casing, additional 20-inch waterline pipe, an additional 40 feet of boring for the waterline, overruns on concrete removal and concrete driveways, and cement stabilized backfill in lieu of cement stabilized base material. The total for the Quantity Adjustments was $ 111,762.70.
The total QA/CO No. 1 amount was $155,695.34 which adjusted the total revised contract price to $26,891,668.69.
This QA/CO No. 2 is for a multitude of items throughout the project such as replacing a fire hydrant, extending an existing driveway, re-routing an 8-inch water line, repairing a waterline break, and re-routing a 12-inch waterline. The total for the change order portion of QA/CO No. 2 is $ 206,426.22.
The quantity adjustment portion for this QA/CO No. 2 is for additional 8-inch waterline pipe, pipe removal, driveways, 5-inch sidewalks, 16-inch pipe removal, adjusting air release valve, pavement markings and removal of pavement markings, 24-inch reinforced concrete pipe, B-mix asphalt over runs, and a credit for MSE retaining walls. The total for the quantity adjustments is $58,888.50.
The total for QA/CO No. 2 is $265,314.72 which adjust the total contract price to $27,156,983.41.
Cost: $265...