Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 3 with Jordan Foster Construction, LLC for the Kenney Fort Boulevard - Segment 4C Project.
Indexes: RR Transportation and Economic Development Corporation (Type B)
Attachments: 1. Resolution, 2. Exhibit A, 3. Map, 4. Form 1295
Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 3 with Jordan Foster Construction, LLC for the Kenney Fort Boulevard - Segment 4C Project.

Body
Change order No. 1 is to include items like removal of metal beam guard fence, provide portable concrete traffic barriers, and temporary pavement markings for the work at Joe DiMaggio and Chandler Creek. Steel encasement pipe was added for the waterline at the new driveway location and the bore for the waterline was extended due to the depth and the close proximity to the proposed NB bridge. This Change Order/Quantity Adjustment is in the amount of $71,028.45.

Change Order/ Quantity Adjustment No. 2 is for the repair and relocation of the reuse water line, additional inlets behind the sidewalk to aid in the drainage near the residential area, including temporary signal at the intersection of Joe DiMaggio and Kenney Fort Boulevard, bores under some driveways and additional Type B pavement. This Change Order was in the amount of $160,469.05. The Quantity Adjustment was in the amount of a negative $5,636.00. The grand total of QA/CO No. 2 was $154,833.05.

Change Order/Quantity Adjustment No. 3 is for the removal of two fire hydrants, the installation of a concrete flume on the backside of the sidewalk, removal of pavement markings, install additional raised pavement markings, modifications to the traffic signals at Joe DiMaggio and Old Settlers Boulevard, and removal of one tree that fell in the roadway during a storm. The quantity adjustments are mainly roadway excavation overruns due to incorrect Engineer calculations of the original plan quantity. The Change Order portion is $74,261.65 and the Quantity Adjustments are $303,072.00. The total amount of QA/CO No. 3 is $377,333.65.

All Change Order and Quantity Adjustments for the project bring the total contract amount to $603,195.15 which is about a 3% overrun.


Cost: $377,333.65
Source of Funds: RR Transpor...