Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with APAC Texas, Inc. - Wheeler Companies for the 2014 Street Maintenance Program (Overlay) Project.
Body
The City Council approved APAC’s bid for construction services for 2014 Street Maintenance Program Overlay at a cost of $5,250,176.25. The scope of the contract included all items necessary for the successful construction of infrastructure and surface improvements for the Greenslopes Subdivision.
Quantity Adjustment/Change Order # 1 is required to add an additional street to the project area; the underlying conditions were found to be inferior and required full depth repair and overlay.
With Quantity Adjustment/Change Order No. 1, the total cost of the construction contract would be $5,301,776.25.
Cost: $51,600.00
Source of Funds: General Self-Financed Construction
Recommended Action
Staff recommends approval.