Consider a resolution authorizing the Mayor to execute a Consulting Services Agreement with HOT Inspection Services, Inc. for the 2016 Lake Creek Ground Storage Tank (GST) Improvements Project.

 

Body

The Lake Creek Ground Storage Tank (GST) provides a reservoir to collect ground water from our three wells and pump the water into the system at a lower cost than Lake Georgetown water.  The Lake Creek GST is in need of a new interior and exterior coating and the tank's interior roof is in need of repair.  Because it was built with rafters and columns, there are many places for rust to begin eroding the tanks interior roof surfaces.  For this reason, during this project, the Utility Staff would like to replace the existing roof with a domed roof that will not need interior supports.  This will lessen the need of having to repair and recoat the interior of the tank every 5 years.                                          

The City’s Utility Staff would like to enter into a contract with HOT Inspection Services, Inc. to provide services to prepare plans/specifications/contract documents, construction administration and inspection services for the rehabilitation and improvements to the 500,000-gallon Lake Creek GST for the amount of $53,500.

Cost: $53,5000

Source of Funds:  Self-Financed Water Construction

 

Recommended Action

Staff Recommends Approval.