Title
Consider a resolution authorizing the Mayor to execute a Contract with Whitestone Civil Construction for the Settlers Crossing Lift Station Bypass Project.
Body
The Settlers Crossing Wastewater Lift station is located on the southwest corner of Red Bud Lane and County Road 122. The lift station was constructed in 2005 to serve a portion of the Settlers Crossing residential subdivision. The lift station is owned and maintained by the City of Round Rock. The property east of the lift station is currently being developed into a residential subdivision. The new subdivision will provide a majority of the infrastructure needed for the existing Settlers Crossing subdivision to gravity flow wastewater to the McNutt Creek wastewater interceptor without the use of the lift station.
On August 11, 2016, Council approved a contract with Garza EMC, LLC to provide design, bidding, and construction phase services for approximately 350 linear feet of 8-inch wastewater line and associated manholes, an 18-inch bore across Red Bud Lane, and decommissioning of the existing lift station.
On June 28, 2017, four bids were submitted and the lowest bid in the amount of $149,951 was submitted by Whitestone Civil Construction.
Cost: $149,951
Source of Funds: Self-Financed Wastewater Construction