Title: Consider a resolution authorizing the Mayor to execute a Standard Form of Agreement between Owner and Contractor with PM Construction & Rehab, LLC dba IPR South Central for the Wastewater Collection System Pipe Bursting Rehabilitation 2020 Project.
Indexes: Self-Financed Wastewater Construction
Attachments: 1. Resolution, 2. Quote, 3. Form 1295, 4. Map

Title

Consider a resolution authorizing the Mayor to execute a Standard Form of Agreement between Owner and Contractor with PM Construction & Rehab, LLC dba IPR South Central for the Wastewater Collection System Pipe Bursting Rehabilitation 2020 Project.

 

Body

The City is required to continue our Wastewater Collection System Rehabilitation program to comply with the Texas Commission the Environmental Quality's Edwards Aquifer Recharge Zone Protection Program. This program requires that the City inspect the wastewater collection system that is located over the Edwards Aquifer every five years and rehabilitate any identified defects in the system. The elimination of defects will not only help to protect the Edwards Aquifer from contamination, but will also reduce inflow and infiltration of ground water and surface water entering the City's wastewater collection system, thereby reducing the City's treatment cost. The City has completed the inspection of four sub-basins to determine areas that require rehabilitation for this project.

The City will perform the work in sub-basins BC-08, BC-21, BC-22Z, and OC-24Z (Egger Acres Subdivision).  This construction contract is based on the developed construction plans and specifications to rehabilitate the wastewater collection system in a portion of these sub-basins. The project includes pipe bursting 11,390 linear feet of existing 6-inch wastewater line with 8-inch High-density Polyethylene Pipe(HDPE) wastewater line and pipe burst 3,750 linear of existing 8-inch wastewater line with 8-inch HDPE wastewater line.

The City is requesting a BuyBoard contract with PM Construction & Rehab, LLC for a total value of $1,443,120.25.

 

Cost: $1,443,120.25

Source of Funds: Self-Financed Wastewater Construction