Title
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 6 with G. Hyatt Construction, Inc. for the Downtown Round Rock Streetscape Improvements Project.
Body
The Transportation Department requests City Council approval for Change Order #6 for the Downtown Streetscape Improvement Project.
Change Order #6 includes a number of items:
1. Power for landscape controls - $1580.70
2. Credit for 8 Dumor Benches - ($12,000.00)
3. Credit for 1 Corten Plate Bridge - ($1,500.00)
4. Tree well protection and replacement of damaged masonry at City Hall - $891.00
5. Portland Cement concrete turndown curb with color - $1,826.55
6. 1xIPE boards for the tops of the QCP walls - $7,541.00
7. Contactor and photocell for lighting - $2,750.96
8. Handrail - round - $$11,733.96
9. Bison IP pedestal and Wood Tiles - $1,683.96
10. Raise Tegan lights - $20,740.36
11. Concrete Wheel Stops - $5,915.00
Original contract price was $2,390,391.58
Change Order #1 added $19,842.20
Change Order #2 added $48,019.40
Change Order #3 added $63,027.80
Change Order #4 added $13,454.32
Change Order #5 added $23,025.11
Change Order #6 adds $41,163.49 for a new contract total of $2,598,923.90.
Cost: $41,163.49
Source of Funds: RR Transportation and Economic Development Corporation (Type B)