Title
Consider a resolution authorizing the Mayor to execute Supplemental Contract No. 1 with BGE, Inc for the Red Bud Lane North Project.
Body
Consider a resolution authorizing the Mayor to execute a supplemental contract with BGE, Inc. for the development of 100% construction Plans, Specifications and Engineering (PS&E) documents for the ultimate construction of a new four-lane divided arterial roadway with off-street shared paths, Red Bud Lane North. This supplemental contract extends the original 30% submittal contract.
This project will upgrade an existing two-lane roadway to a new four-lane divided including: intersection, curb and gutter, and pedestrian improvements. Design should be completed in 2021 with construction to begin in 2022.
The original contract with BGE, Inc. for the schematic work on project to bring the plans to 30% complete was for $436,411.52. To bring the plans to 100% completion, this supplemental is for $689,788.50. This brings the total project cost to $1,126,200.02.
Cost: $689,788.50
Source of Funds: RR Transportation and Economic Development Corporation