Title
Consider a resolution authorizing the Mayor to execute a Contract with Andale Construction for the 2021 Street Maintenance Program - Project A High Density Mineral Bond Overlay.
Body
Bids for the referenced project were opened on June 4, 2021 at 10 a.m. One (1) responsive bid proposal was received. The bid was opened and read aloud. The submittal was checked for the inclusion of the Statement of Bidder's Safety Experience and bid guarantee. The total bid price was $689,828.00.
Andale Construction: $689,828.00
Andale Construction is the apparent low bidder. The engineer's estimate of probable construction cost for this project at bid time was $733,128.00. Based upon staff review of the attached Bid Tabulation, we recommend the City of Round Rock accept Andale Construction's bid for contract award in the amount of $689,828.00.
Cost: $689,828.00
Source of Funds: General Self-Financed Construction