File #: 2021-213   
Type: Resolution Status: Agenda Ready
File created: 7/26/2021 In control: City Council
On agenda: 8/12/2021 Final action:
Title: Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Chasco Constructors for the Kenney Fort Boulevard Segment 4B Project.
Indexes: RR Transportation and Economic Development Corporation (Type B)
Attachments: 1. Resolution, 2. Exhibit A, 3. Form 1295, 4. Map

Title

Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Chasco Constructors for the Kenney Fort Boulevard Segment 4B Project.

 

Body

The City of Round Rock entered into a contract with Chasco Constructors for the construction of Kenney Fort Boulevard Segment 4B on June 25th, 2020. An NTP was issued August 19th, 2020 to commence work.

This Change Order #1 is for additional select fill material that was used to fill for some over excavation to remove fatty clay material, reduction of base material, construct a French drain, add a concrete flume, add some embankment, and add some sidewalk, removal of asphalt paving, and seed broadcasting.  The amount of this Change Order/Quantity Adjustment is $77,701.70.  This will bring the total contract price to $3,626,259.45.

 

 

Cost: $77,701.70

Source of Funds: RR Transportation and Economic Development Corporation