File #: 2021-258   
Type: Resolution Status: Approved
File created: 9/2/2021 In control: City Council
On agenda: 9/23/2021 Final action: 9/23/2021
Title: Consider a resolution authorizing the Mayor to execute a Contract with J.D. Abrams, LP for the Kenney Fort Boulevard Segments 2&3 Project.
Indexes: RR Transportation and Economic Development Corporation (Type B), Self-Financed Wastewater Construction, Self-Financed Water Construction
Attachments: 1. Resolution, 2. Bid Tab, 3. Award Recommendation, 4. Williamson Concur to Award, 5. Updated map, 6. Form 1295

Title

Consider a resolution authorizing the Mayor to execute a Contract with J.D. Abrams, LP for the Kenney Fort Boulevard Segments 2&3 Project.

 

Body

The City opened bids for the Kenney Fort Blvd Segments 2 & 3 Project on Tuesday July 27th, at 2:00 PM. There were four (4) responsive bids and one (1) unresponsive bid. The bids ranged from $23,409,120.97 to $25,741,680.95. The submitted bid form has been checked for accuracy and compliance with the requirements of the bidding instructions. CP&Y recommends the City of Round Rock award the contract to the apparent low bidder - J.D. Abrams. The Utility Department has elected to use the base bids in the contract. This project is funded through the Type B program with additional funds from the Federal Surface Transportation Block Grant (STBG) program through CAMPO.

 

Bids Submitted:

 

J.D. Abrams - $23,409,120.97

Chasco - $24,219,866.85

Jordan Foster - $24,492,502.40

CC Carlton Industries - $25,741,680.95

Capital Excacation - Unresponsive

 

 

Cost: $23,409,120.97

Source of Funds: RR Transportation and Economic Development Corporation, Self-Financed Water Construction, and Self-Financed Wastewater Construction