Title: Consider a resolution authorizing the Mayor to execute a Contract for Engineering Services with Kimley-Horn and Associates, Inc. for the Kenney Fort 24-inch Reuse Line Extension Project.
Indexes: Self-Financed Water Construction
Attachments: 1. Resolution, 2. Exhibit A, 3. Map, 4. Form 1295

Title

Consider a resolution authorizing the Mayor to execute a Contract for Engineering Services with Kimley-Horn and Associates, Inc. for the Kenney Fort 24-inch Reuse Line Extension Project.

 

Body

This 24-inch reuse water transmission line will extend the reuse water system south along Kenney Fort Boulevard down to Forest Creek Drive.  At Forest Creek Drive, the reuse water line will connect to another 24-inch line being constructed as a part of the Kenney Fort Boulevard extension from Forest Creek Drive to Gattis School Road. Reuse water customers at this south extension of the reuse water system could potentially include Cedar Ridge High School, data processing centers, and other future businesses in this area of Round Rock.  This will ultimately provide a looped system for all reuse water customers along Louis Henna Boulevard and over to south Mays Street.

 

 

Cost: $616,200